Liquidated damages clauses are often attacked in common law jurisdictions for being unenforceable "penalties". The test for what constitutes a "penalty" has been reviewed in common law jurisdictions over recent years. Last month, the Singapore Court of Appeal gave welcome clarity to the penalty test in that country.
Background: The rule against penalties
A contractual breach can create a host of issues, not only over liability, but also the consequences arising out of it. To provide some certainty, parties often stipulate in the contract what damages one party has to pay if it breaches the contract in a certain way. Such provisions are commonly known as liquidated damages clauses, because the clause defines or "liquidates" the damages that are payable.
In drafting liquidated damages clauses, parties in common law jurisdictions need to be conscious of the rule against penalties, which could operate to render such clauses unenforceable. The traditional common law position has been that:
- a liquidated damages clause, which represents a genuine pre-estimate of loss or damage, will be upheld; while
- a payment required by a contract that has the effect of penalising the party in breach (and going beyond compensating the innocent party for its loss) will be considered a penalty, and will not be enforced by a court or tribunal.
The distinction between a legitimate liquidated damages clause and a penalty clause has long been debated.
- One fundamental issue is in what circumstances the law treats a contractual compensation clause as going beyond "compensation" and becoming financial "punishment".
- Another issue is whether the penalties rule can apply where an obligation to pay money arises from a matter that is not a breach of contract. Both of these issues were addressed in the Denka case.
Denka Advantech Pte Ltd v Seraya Energy Pte Ltd [2020] SGCA 119
Relevant Facts
The dispute arose out of three electricity retail agreements (ERAs) for the sale and purchase of electricity in Singapore between Seraya (the electricity retailer) and Denka (the power purchaser).
- Each of the ERAs contained a liquidated damages clause that applied if it was terminated.
- In 2014, Denka sought to stop purchasing electricity under the ERAs because the price was significantly higher than the market price.
- Seraya claimed that Denka's conduct was a repudiatory breach of the ERAs, and started litigation against Denka for the breach/repudiation (which Denka denied).
- Seraya claimed liquidated damages under the ERAs. The liquidated damages payable were determined by the formula: A x B x 40%, where A referred to the number of months between the date the contract was terminated and the contract's expiration date; and B was the arithmetic average of the amount payable by Denka in a stipulated period prior to termination. Expert evidence led by Seraya showed that the 40% multiplier produced an amount of liquidated damages within the range of loss that Seraya might have reasonably incurred due to a termination of the ERAs.
- Denka contended that even if it had breached/repudiated the ERAs, no liquidated damages were payable because the relevant provisions of the ERAs operated as penalties.
Decision
There were two principal aspects to the Singapore Court of Appeal's decision.
- First, the Court confirmed that the rule against penalties will only apply where a clause, in substance, requires a party to pay a liquidated sum for breaching the contract. Under Singapore law, the penalties rule does not apply where a contract requires money to be paid in situations not involving (in substance) a breach of contract.
- Second, the Court of Appeal confirmed that the legal test for a penalty under Singapore law is (and remains) the test from the English case of Dunlop Pneumatic Tyre Company Ltd v New Garage and Motor Company Ltd [1915] AC 79, i.e. "if the sum stipulated for is extravagant and unconscionable in amount in comparison with the greatest loss that could conceivably be proved to have followed from the breach".
The Dunlop test therefore requires a comparison to be made between:
(a) the amount of liquidated damages payable; and
(b) the greatest conceivable loss that could flow from the breach.
If (a) exceeds (b), the clause may be considered a penalty.
Significantly, the Singapore Court of Appeal declined to adopt the wider approach developed by the UK Supreme Court in Cavendish Square Holding BV v Makdessi [2016] AC 1172. In Makdessi, the UK Supreme Court reasoned that even if (a) exceeds (b), a liquidated damages clause may not be considered a penalty if it can be construed as protecting the "legitimate interest" of the innocent party, as opposed to seeking to punish the party in breach of contract. The Court of Appeal regarded the "legitimate interest" test as being too vague and general a concept to apply.
Commercial Implications
The Denka case has several implications for contracts where Singapore law applies.
First, the decision means that the penalties rule cannot be applied where a contract requires the payment of money for something that does not, in substance, amount to a breach of contract. This could be the case, for example, where an energy supply contract includes a "take or pay" provision. An offtaker's failure to take a certain amount of energy will not usually constitute a breach of contract, so the corresponding obligation for it to pay for energy that it never took is unlikely to be struck down as a penalty.
Secondly, although the Court of Appeal did not adopt the English "legitimate interest" test, this does not make it any easier to identify (and advise) when a liquidated damages clause constitutes a penalty. The question of whether stipulated damages are "extravagant and unconscionable" compared with the greatest hypothetical loss that could be suffered inevitably involves numerous imponderables and a large measure of speculation. The penalties doctrine involves shades on a spectrum as opposed to sharp, identifiable lines between enforceable "liquidated damages" and unenforceable "penalties".
Thirdly and most importantly, as Denka demonstrates, the general disposition of the common law courts (those of Singapore and elsewhere) towards attacks on the enforceability of liquidated damages clauses is one of initial scepticism. This is particularly so where the parties are sophisticated business people who are capable of protecting their commercial interests through negotiating acceptable terms. A contracting party has a high hurdle to clear in persuading a commercial court that an agreed liquidated damages clause is "extravagant and unconscionable".
To solidify the conclusion that a liquidated damages clause does constitute a "genuine pre-estimate" of loss and not a penalty, a party could, during contract negotiations, endeavour to furnish information/calculations setting out its expected losses in the event of a breach of contract. This could even be incorporated into the contract in some form, to link the amount of liquidated damages in the contract to such information/calculations.
This publication is provided for your convenience and does not constitute legal advice. This publication is protected by copyright.
© 2021 White & Case LLP