Find, Fix and Track Entity, Docket No. RC11-6 (September 30, 2011)
Reliability Standard: TPL-002-0
Requirement: R1
Region: RFC
Issue: As the result of a compliance audit, RFC determined FFT Entity violated R1 because it failed to provide evidence that it performed a stability assessment for system performance in accordance with Table I for Category B contingencies.
Finding: RFC found that this issue constituted only a minimal risk to bulk power system reliability because it was only a documentation issue as the FFT Entity had performed a stability assessment and coordinated its operating procedure with its RC on multiple occasions.